09-09-2026 Council Questions
Town Council Meeting
September 9, 2026
Responses to Council Agenda Questions
1. Will the new contract for the archives of the planning dept cause a delay in the launch of
the new OpenGov system for the existing funded project?
o This is added work that should be completed before launch because it includes not
just archives but current and active records as well. It should not cause a delay
because other implementation work is still ongoing in parallel. When we launch, we
will switch everything at once, so the Town is fully operating in OpenGov from day
one.
2. Are the Good City and CSG (Joaquin) consultants already familiar with OpenGov, in
general?
o Good City and CSG are planning and building consultants rather than OpenGov
implementation specialists, which is why training for all staff and consultants is
included as part of the original implementation contract. We won't go live until they
are trained on how our specific OpenGov system is configured and works.
3. What is the schedule for completion of the original work and the new work?
o The archive and data migration work will run concurrently with other
implementation tasks rather than sequentially, so there is no separate standalone
schedule for this scope. All workstreams are being tracked together and will
converge at launch, which we anticipate occurring between October and December
of this year.
4. What approximate date will the planning & building dept be cutting over from energov to
open gov permanently?
o We have not committed to an exact launch date because competing demands,
including Council and Commission meetings, active permits, and other planning
efforts, have at times required us to prioritize other work alongside implementation.
This is the reality of running a small department while simultaneously managing a
major system transition. With that said, we remain on track to launch between
October and December and will announce the specific date once it is confirmed.
5. I understand the new need in this situation to enable use of our archives but remain
concerned about our budget situation.
o First, this data migration is not just for use of our archives, it is a requirement that
the Planning and Building Department maintain planning and building records in
accordance with California law and any other Town requirements. Second, when
the original budget amendment went to Council in February for OpenGov and its
implementation, a 10% contingency was built in specifically to accommodate
unanticipated work that emerges during implementation, such as this data
migration need. It is common in a complex implementation like this for additional
requirements to surface once the process is underway, and the full scope of needs
becomes clear. In addition to the contingency, we have been under budget in other
aspects of the implementation work, so between that and the 10% contingency,
there is funding in the existing budget without the need for a budget amendment.