11-16-2026 Council Docs
11/17/2026
Claude summary of the CPUC Rate document that is linked on pg. 20 of this PDF (from
Nov. 19, 2026 Public Utilities Commission of the State of California Agenda Packet)
Application 26 -02-005 DECISION ADOPTING A DDITIONAL RULES FOR THE SENATE BILL
884 EXPEDITED UTILITY D ISTRIBUTION INFRASTRUCTURE UNDERGROUNDING
PROGRAM
The de cision in plain terms
The s ituation: A 2 024 state law lets the three big electric utilities (PG&E, Southern
California Edison, San Diego Gas & Electric) get a fast-track review of 10-year plans to bury
power lines in high fire-risk areas. The state utilities commission has to decide how to judge
whether a given burial project is worth the money, how to check the utilities' spending
afterward, and what happens if a project costs more than promised. This decision sets
those rules.
What t he rules s ay:
1. J
udging whether a project is worth it. Every utility must use the same math to
compare a project's benefits (fewer fires, fewer outages, lower maintenance)
against its costs. Maintenance savings count as a benefit, extra maintenance costs
count as a cost, and the same discount rate applies to everything. Outage value is
based on the customers actually in the affected areas, not the whole system.
2. Checking the spending afterward. An independent auditor reviews each individual.
project. The utilities wanted a statistical sample of the whole portfolio. The
commission said no and also denied their request for a 2% cushion on the annual
spending limit.
3. Five new conditions for recovering costs from customers. A project's costs can't
be recovered if:
o it was not at least as cost-effective as the best alternative, such as covered
wires or tree trimming;
o its actual cost is more than 30% above the forecast;
o its actual benefit-to-cost ratio is more than 30% below the forecast; or
o its forecast ratio falls below 1, meaning costs exceed benefits.
4. No "local factors" exception. Utilities can't pick burial over a better alternative just
because of reasons outside the risk models.
Who benefits
The rules mostly favor the parties who pushed for tighter oversight:
• Electricity customers generally. Customers pay for this program through their
bills, and the new conditions give the commission a way to refuse or refund costs for
projects that overrun or weren't the best choice. The decision says that without
these conditions, nothing would protect customers when burial is chosen over a
cheaper, equally effective option.
• The groups that argued for these rules: the state's consumer advocate office, the
consumer group TURN, large industrial energy users, and telephone/cable
providers. Their positions on project-level audits and conditions are largely what the
decision adopted. The communications companies argued the utilities shouldn't
impose costs on third parties without showing each project is worth it.
• Communities in high fire -risk areas, indirectly. If the rules work, money goes to
the projects that reduce the most risk per dollar rather than whichever projects a
utility prefers.
The utilities lose flexibility. They argued for managing the program as a whole portfolio,
where a bad project can be offset by good ones, and for oversight at that level only. The
decision rejects that for the cost-recovery conditions.
On PG&E's opposition
I can't confirm PG&E's current stance from this document. The three utilities filed jointly
and argued together, so the opposition appears as the "Joint" position rather than PG&E
alone. The document shows them opposing project-level conditions, project-level audits
and the other points above. It doesn't include their reaction to this proposed decision,
since comments on it are filed afterward and aren't part of the text. Their objections will
likely show up in those comments, or in a revised decision if the commission changes it
before voting.
One correction to my last answer: I said PG&E's general rate case is where its
undergrounding costs are "currently being addressed. " The document only lists that case in
a footnote, in the context of keeping previously funded work out of this program. I shouldn't
have said more than that.
Detailed Summary of the 160 page cocument
I'm skimming this 160-page proposed decision on SB 884 undergrounding, and next I'm
pulling the key rulings from each section and the order.
Now the Conclusions of Law, which hold the actual rulings.
Summary: Proposed Decision on SB 884 Undergrounding Rules (A.26 -02-005)
What it is: A 160-page proposed decision by Commissioner John Reynolds, mailed
October 16, 2026. It has no legal effect unless the CPUC votes to approve it, and it could be
heard as early as the November 19, 2026 Business Meeting. It resolves the joint
application of PG&E, SCE and SDG&E, filed in February 2026 as directed by Resolution
SPD-37. It closes the proceeding.
Background: SB 884 created an optional, expedited pathway for the three large utilities to
get review of 10-year plans to move overhead distribution lines underground in Tier 2 and 3
High Fire-Threat Districts and wildfire rebuild areas. In Phase 1, Energy Safety approves the
plan. In Phase 2, the CPUC conditionally approves costs, and approved costs are recorded
to a one-way balancing account with no after-the-fact reasonableness review. In Phase 3
the utility builds the plan and the costs are audited. This decision sets the rules for how
benefits are calculated, how the audit works, and what additional conditions apply.
1. Benefit -Cost Ratio (BCR) methodology
The decision standardizes the BCR calculation across all three utilities:
• O&M: O&M savings go in the numerator as a benefit, and incremental O&M costs go
in the denominator. Utilities must report each separately.
• Risk scaling: Unscaled, risk-neutral values are used until the CPUC adopts
something else in the new RDF proceeding (R.26-04-016).
• Reliability value (ICE Calculator): Version 2.0 is used for now, with separate values
for HFTD and non-HFTD areas and for residential and non-residential customers.
The values are based on the eligible-area customer population, not the system-wide
population the utilities proposed.
• Discount rate: A single rate, the utility's WACC, applies to everything.
• Backcasting: Forecast BCRs and unit costs are recalculated at the risk reporting
unit (RRU) level so forecast and actual values compare like with like.
• Other definitions: Net salvage value is included in costs, and present value revenue
requirement (PVRR) is used. "Year Zero" is the year a project becomes used and
useful. Everything is measured against a "No-Build Baseline" of the existing system
with already-funded mitigations.
2. Audit framework
• The audit is done at the project/RRU level. The utilities' proposal for portfolio-level
statistical sampling is rejected.
• There is a single audit report, filed in the utility's plan proceeding. It must follow
Generally Accepted Government Auditing Standards (GAGAS), and the benefits side
of the BCR is audited too.
• Cost cap, third-party funding offsets, average unit cost, and average BCR are each
verified under defined methods. The utilities' request for 2% variance thresholds on
the annual cost cap is denied.
• Incrementality is checked by comparing GRC-authorized undergrounding mileage
(not just dollars) against the mileage proposed in the plan.
3. Five new Phase 2 Conditions (#6 –#10)
• #6: Costs must be tied to projects whose forecast BCR was at least that of the best
alternative mitigation.
• #7: Re-evaluate the best alternative if a project's Screen 4 BCR drops below it.
• #8: A project's actual BCR can't be more than 30% below its Screen 4 forecast.
• #9: A project's actual unit cost can't be more than 30% above its Screen 4 forecast.
• #10: A project's Screen 4 BCR must stay at or above 1.
The 30% threshold is set slightly tighter than the upper bound of the AACE Class 4 estimate
range (-30% to +50%).
4. Other rulings
• The utilities' request to weigh "local factors" outside the risk models when an
undergrounding BCR is within 70% of an alternative's is rejected .
• Previously scoped or funded projects can be recorded to the plan's balancing
account only if they are incremental to costs authorized in a GRC or other
proceeding. Any previously authorized scope must be reflected in the No-Build
Baseline.
Ordering paragraphs
1. The utilities must follow SPD-15, SPD-37 and the associated guidelines, as revised
here, when filing their 10-year plans.
2. Within 45 days of the decision's effective date, each utility must file a Tier 2 Advice
Letter listing qualified auditors and showing how they meet the audit standards.
3. The proceeding is closed.
I read the summary, background, conclusions of law and order closely, and skimmed the
discussion sections. I can go deeper on a particular section, such as the parties' positions
on discount rate or risk scaling.
Cost to consumers?
This decision doesn't state a cost to consumers. It contains no bill impacts, no rate
increases, and no total program cost. The only dollar figure in the whole document is an
unrelated reference to a PG&E catastrophe bond.
That's because it sets rules , not dollar amounts. The cost numbers come later, in each
utility's Phase 2 Application, when the CPUC decides whether to conditionally approve a
10-year plan's costs. At that point it sets the actual annual cost cap, the average unit cost
limit, and the minimum average BCR. None of those exist yet, and the decision says they
will be fixed in the Phase 2 decision.
What the decision does say about consumer exposure:
• Ratepayers pay. Costs recorded to the program's one-way balancing account are
recovered through rates, and the account is not subject to after-the-fact
reasonableness review. The decision relies on the Phase 2 Conditions and the audit
as the protection instead.
• New limits on overruns. The five new conditions block recovery for projects that
are less cost-effective than alternatives, have actual unit costs more than 30%
above their Screen 4 forecast, or have actual BCRs more than 30% below it.
• Refunds are possible. If an audit finds costs were recorded incorrectly or failed the
conditions, the CPUC may order a refund. The details, such as frequency, true-up
and refund mechanism, are left to the Phase 2 proceeding.
• Third -party funding offsets the cap. Any such funding received reduces the annual
cost cap for that year.
• Costs already approved elsewhere can't be double -counted. Previously scoped
or funded undergrounding can only be recorded if it is incremental to what was
authorized in a general rate case.
To see actual dollar exposure, look at the utilities' 10-year plans at Energy Safety, and at
their Phase 2 Applications once filed. PG&E's pending general rate case (A.25-05-009) is
also where its undergrounding costs are currently being addressed for rates.
Matters of Public Interest
For the convenience of the public and media representatives, items of widespread public interest will be taken up at the
beginning of the meeting.
For further information contact the Public Advisor
(415) 703-2074 E-mail: public.advisor@cpuc.ca.gov
This location is accessible to people with disabilities. If specialized accommodations for the disabled are needed, e.g.
sign language interpreters, please call the Public Advisor at (415) 703-2074 or TTY # (415) 703-5282 or toll free # 1-
866-836-7825 three business days in advance of the meeting.
Public Utilities Commission of the State of California
Public Agenda 3590
Thursday, November 19, 2026, 11:00 a.m.
801 Capitol Mall
Sacramento, California
Commissioners
John Reynolds, President
Matthew Baker
Karen Douglas
Christine Harada
Darcie L. Houck
For each agenda item, a summary of the proposed action is included; the Commission's decision may, however, differ from that